What is Vibro Replacement

Vibro Replacement is a ground improvement technique that is used to build Stone Columns that increase soil strength and reduce its compressibility.  This technique is one of the most widely used ground improvement methods in the world.  Historically, this method has been used to densify loose granular soils, but over the years, the method has been used increasingly to reinforce a wide range of soil types using stone columns.

Installing Stone Columns could be completed using two main methods: 

Wet Top Feed Method: This is done using a vibrating probe inserted in the ground with the help of jetted water that breaks down the pores of the surrounding soil, thereby densifying the soil. The crushed stones or the gravel that is poured in takes the place of the soil and keeps up the pressure on the soil that was created by the vibrating probe. These columns are made across the area to be built in a grid or engineered patterns at regular intervals.

Dry Bottom Feed Method:This is done using a vibrating probe inserted in the ground with the help of compressed air. The crushed stones or the gravel that is poured in takes the place of the soil and keeps up the pressure on the soil that was created by the vibrating probe. These columns are made across the area to be built in a grid or engineered patterns at regular intervals.

Benefits

Reduce and control total and differential foundation settlement
Increase soil bearing capacity, leading to smaller foundation sizes.
Increase soil stiffness and strength
Reduce liquefaction risk
Improve slope stability
Reduce permeability

Applications

Recommended for sites with variable layer of sands, silts, and clay.
Effective for seismic mitigation under structures or embankments.
Suitable for low to mid-rise new construction buildings.
Applicable for area loads, including tanks and embankments.
Can be used to address sinkhole triggering and collapse.
Highly cost-effective when compared to deep foundation systems.
Vibro replacement machinery at work ground

It's Time To Build...What to Expect

Geotek Design-Build will develop and provided a signed and sealed design detailing Vibro Replacement plan.
Site clearing and access preparation will precede the Vibro Replacement process. Typically prepared by site contractor.
A 2” water may be necessary and shall be provided to Geotek Design-Build.
Wet method, and depending on site conditions, water control procedures are needed
#57 Stone is used to backfill.
Substantial quantities of rock backfill are necessary, necessitating site access for deliveries by rock trucks
Vibro Replacement is generally performed under a performance specification, with specified minimum improvement criteria.
Post-treatment testing, SPTs or CPTs, is recommended to validate specified requirements.
Full-Scale Plate load testing can also be performed to verify bearing capacity and settlement requirements.
After our work is completed and testing is done, Geotek Design-Build provide a certification package to allow final site grading and foundation construction to begin.

Process

Vibro Replacement offers a cost-effective and efficient solution in cases where it is applicable, serving as a viable alternative to deep foundation systems.  In summary, Vibro Replacement offers a range of benefits, including increased bearing capacity, settlement control, time and cost savings, environmental friendliness, versatility, and enhanced stability. These advantages make Vibro Replacement a valuable technique in ground improvement projects, ensuring the stability and durability of structures while optimizing construction efficiency.

Step 1 Step 2 Step 3

Vibro Replacecment offers a cost-effective and efficient solution in cases where it is applicable, serving as a viable alternative to deep foundation systems.  In summary, Vibro Replacement offers a range of benefits, including increased bearing capacity, settlement control, time and cost savings, environmental friendliness, versatility, and enhanced stability. These advantages make Vibro Replacement a valuable technique in ground improvement projects, ensuring the stability and durability of structures while optimizing construction efficiency.

After penetration to the design depth, the Vibro Probe is partly or fully withdrawn, and the hole created by the vibrator is filled with stones. The Vibro-Probe is withdrawn in lifts (1 to 3 ft. lifts) and lowered into the stone. With its design nose cone, the Vibro-Probe displaces the stone both radially and downwards into the surrounding soil, thereby causing displacement of the soil over and above that created by the initial penetration of the Vibro Probe. In this way, a compact column of stone interlocked with the surrounding ground is built up to the ground surface.

The jetted water creates an annulus around the Vibro Probe and stones are pushed into the created hole from working grade. The process requires well-draining soil near working to allow jetted water that returns to the surface to drain into the soil.

Design and Quality Control

Vibro Replacement is used when in-situ soil is not suitable for densification through Vibro Compaction.  This is typically due to the relatively large amount of fines and presence of organic soils.  Stone columns are cohesionless; therefore, its stiffness depends upon the lateral support given by the soil around it.  Soil reinforced with stone columns will act as a composite medium, exhibit increasing stiffness and strength as stone column spacing is reduced, column cross-sectional area increases, and angle of friction of imported stone increases.

The construction process of Vibro Replacement Stone Columns affects to a certain extent their performance.  The following aspects are of particular importance and should be carefully evaluated during construction

  • The As-Built diameter of the stone column
  • The influence of the stone column installation of the surrounding ground and on previously installed column

Recording of backfill quantity in each column is essential for determining column diameter.  On completion, the total volume of the column is correlated with the total volume of backfill less any surface wastage.  To assure that the maximum practical compacted column diameter is reached, a continuous reading of the vibrator’s pressure or ammeter should be taken, and the probe should be lifted and dropped several times after each layer of stone has been added.

The performance of the Vibro Replacement ground improvement system is quantified using Post Treatment SPT or CPT test or using a full-scale load test on a group of Stone Columns.

Visual Portfolio, Posts & Image Gallery for WordPress
Select the fields to be shown. Others will be hidden. Drag and drop to rearrange the order.
  • Image
  • SKU
  • Rating
  • Price
  • Stock
  • Availability
  • Add to cart
  • Description
  • Content
  • Weight
  • Dimensions
  • Additional information
Click outside to hide the comparison bar
Compare